Share

The upgrade of the Tamworth substation is now complete, the largest of five substations to undergo works as part of the Transgrid Queensland-NSW Interconnector (QNI) project.

Transgrid’s Executive Manager of Delivery, Craig Stallan, said, “QNI is 90 percent complete and we’re on track to have all project works completed by May 2022.

“Since the Australian Energy Market Operator (AEMO) first recognised QNI as a priority in their 2020 Integrated System Plan, and work started later that year, we’ve increased the Tamworth substation footprint by 50 per cent to accommodate the technology required to help future-proof this part of our grid.”

The technology called Static Var Compensators, or SVC’s, which are vital in controlling reactive power flows on the grid, have been installed at Tamworth and Dumaresq substations. 

A team of experts from Siemens Energy in India arrived in December 2021, and once their work is complete, the SVCs can be energised and tested. 

Following this, the project will be handed over to AEMO for rigorous inter-regional testing.

Over 300km of transmission lines have been updated to higher temperature ratings, which means they can now accommodate higher power transfers while maintaining statutory ground clearances for the higher temperatures. 

58 transmission towers were replaced and 131 existing towers were uprated as part of the project.

“The QNI transmission lines were uprated to 120°C, which will allow higher power flows between the states, vital in times of extra demand, and it will help to stabilise energy prices,” Mr Stallan said.

QNI also involves the installation of new capacitor banks, SVC transformers and associated 330kV switch bays. 

The capacitor banks provide additional reactive power, while the SVC regulates the reactive power on the grid.

“This technology will optimise the real power flows on the transmission lines as well as providing grid stability,” Mr Stallan said.

“For the past two years we have been part of the local communities where major substation upgrades have occurred, particularly at Tamworth, Armidale and Dumaresq, employing up to 170 extra people at any one time on QNI.”

For more information about the QNI project visit https://transgrid.com.au/qni .

Related articles
0 Comments

Leave a reply

Your email address will not be published. Required fields are marked *

*


The reCAPTCHA verification period has expired. Please reload the page.

©2024 Energy Magazine. All rights reserved

CONTACT US

We're not around right now. But you can send us an email and we'll get back to you, asap.

Sending

Log in with your credentials

Forgot your details?