• About
  • Advertise
  • Subscribe
  • Contact
  • Events
Saturday, January 24, 2026
Newsletter
SUBSCRIBE
  • News
    • Events
  • Features
  • Electricity
  • Gas
  • Renewables
    • Batteries & Storage
    • Hydro Power
    • Hydrogen
    • Solar
    • Wind
  • Smart Energy
No Results
View All Results
  • News
    • Events
  • Features
  • Electricity
  • Gas
  • Renewables
    • Batteries & Storage
    • Hydro Power
    • Hydrogen
    • Solar
    • Wind
  • Smart Energy
No Results
View All Results
Home Renewable Energy Hydro Power

Works progressing on Kidston Pumped Hydro

by Kody Cook
December 12, 2023
in Batteries & Storage, Electricity, Hydro Power, News, Projects, Renewable Energy, Spotlight
Reading Time: 3 mins read
A A
Share on FacebookShare on Twitter

Genex Power has released an update on the construction of its 250MW/2,000MWh Kidston Pumped Storage Hydro Project.

Genex’s Engineering, Procurement and Construction (EPC) Contractor continues to progress the underground excavation works and remains on schedule for completion in the second half of 2024.

As at 4 th December 2023, the following works were fully completed

  • Main Access Tunnel
  • Construction adits 1, 2, 3, 4 and 5
  • Transformer hall and IPB breakthroughs into the powerhouse cavern
  • Headrace tunnels 1 and 2
  • Intake shaft 1, the ventilation shaft and the cable shaft

The excavation of the powerhouse cavern is now over 65 per cent complete and is anticipated to be fully excavated in early 2024. The second intake shaft is over 50 per cent complete and will be fully excavated in January 2024.

Works have also commenced from construction for the excavation of the first sections of tailrace tunnels 1 and 2, heading back toward the powerhouse cavern, anticipated to be completed in early 2024.

Once completed, this will signal the completion of all major underground excavation works for the project.

The final excavation of tailrace 1 and 2 from construction adit 2 towards the ultimate portals in Eldridge Pit is anticipated to be completed in 1H CY2024 once the water level has been sufficiently lowered in Eldridge Pit.

Works are also currently underway on the installation of the gantry crane running rails. 

Installation and commissioning of the 220t gantry crane is scheduled to be completed in January 2024 to allow the powerhouse fit out works to commence. 

The powerhouse fit out works will start with the installation of embedded parts for the draft tube steel liner sections which ultimately connect with the tailrace tunnels.

Wises Dam works are also being progressed by the EPC Contractor. All bulk earthworks, concrete plinth and cement screeding have been completed for the full 6km circumference of the dam. 

The final task is to complete the liner placement which is 85 per cent complete. It is anticipated that Wises Dam will be fully completed early in 2024.

The dewatering works have continued, with six 850kW pumps delivering approximately 1,700L/s into Wises Dam. These will continue into the new year to allow the commencement of the tailrace works from underground to the portals in the bottom of Eldridge Pit.

Genex has also said that transmission works are progressing well. 

The balance of electrical plant works being undertaken by Beon Energy Solutions have been completed, with the finalisation of stringing of the conductor from the new K2H switching station to the Aurumfield (K2X) substation. This has enabled Genex to grant practical completion to Beon for these works.

Powerlink has reached several construction milestones, including most notably the completion of the Guybal Munjan substation at the Mt Fox end of the new transmission line.

Concurrently, works are progressing well at the K2X substation at Kidston, with completion scheduled in the second quarter of 2024. 

This substation will ultimately contain an area for equipment to connect the 258MW Kidston Stage 3 Wind Project to the National Electricity Market.

In addition to the substation works, Powerlink has continued to progress the 185km 275kV transmission line works with all of the towers in Zone 1 at Kidston erected to allow the commencement of conductor stringing from the Kidston end of the alignment. 

Works continue with foundations, and tower assembly and erection for the remainder of the alignment.

Featured image: Aerial view of the Wises Dam. Image credit: Genex Power.

Related Posts

Origin Eraring

Eraring coal-fired power station extended to 2029

by Tom Parker
January 20, 2026

Origin Energy will continue operations from all four units of the Eraring coal-fired power station until April 2029 due to...

Cheaper Home Batteries scheme

What a soaring Cheaper Home Batteries scheme means for prices

by Tom Parker
January 20, 2026

The Cheaper Home Batteries scheme has seen meteoric uptake in its first six months, with 200,000 installations since it was...

BESS

‘Extremely competitive’: How the Australian BESS market is rapidly changing

by Tom Parker
January 19, 2026

International players see Australia as a key renewable energy hotspot, particularly in the BESS (battery energy storage system) game. A...

Read our magazine

Join our newsletter

View our privacy policy, collection notice and terms and conditions to understand how we use your personal information.
Energy is a thought-leading, technology-neutral magazine, developed to help the industry answer some of the Energy sector critical questions it is currently grappling with.

Subscribe to our newsletter

View our privacy policy, collection notice and terms and conditions to understand how we use your personal information.

About Energy

  • About
  • Advertise
  • Subscribe
  • Events
  • Contact
  • Digital Magazine
  • Terms & Conditions
  • Privacy Collection Notice
  • Privacy Policy

Popular Topics

  • News
  • Spotlight
  • Renewable Energy
  • Electricity
  • Projects
  • Networks
  • Sustainability
  • Gas

© 2026 All Rights Reserved. All content published on this site is the property of Prime Creative Media. Unauthorised reproduction is prohibited

No Results
View All Results
NEWSLETTER
SUBSCRIBE
  • News
    • Events
  • Features
  • Electricity
  • Gas
  • Renewables
    • Batteries & Storage
    • Hydro Power
    • Hydrogen
    • Solar
    • Wind
  • Smart Energy
  • About
  • Advertise
  • Subscribe
  • Contact
  • Events
  • Newsletter

© 2026 All Rights Reserved. All content published on this site is the property of Prime Creative Media. Unauthorised reproduction is prohibited