Works are underway on a large-scale project by SA Power Networks, which includes a new substation at St Kilda for national defence purposes.

The new substation is intended to help deliver a land-based test facility for the Navy’s new Hunter Class frigates.

Once completed, the 66kV to 11kV substation will power the testing facility of the Hunter program’s combat systems, which is delivering nine world-class anti-submarine warfare frigates to keep Australia safe.

The Network Project Manager for the project, Sinisa Culibrk, said the St Kilda substation brings together many parts of the business to deliver for an important customer and national defence project. 

“As part of the project, we are building a new, dedicated substation to provide the required load for the new Defence Training Centre,” Mr Culibrk said. 

“To provide the substation with the supply, we had to build 1.8km of overhead 66kV line.”

At SA Power Networks, Field Services have liaised closely with Network to manage customer expectations and to coordinate a complex 66kV connection that integrates into the network in the northern suburbs.

SA Power Networks’ civil contractors have dug the earth grid and prepared the work for the civil team to start the primary footing works. 

Delivery Project Manager, Andrew Smith, said the project is an extraordinary example of how different parts of the company come together and deliver when it’s needed.

“The civil team pressed hard to accelerate the work, overcoming weather problems, resourcing issues to meet the project timeline with the transformers and control building successfully delivering to site as planned in January,” Mr Smith said.

Despite the efficient delivery, tidal groundwater located at just 800mm below the surface has been an ever-present risk.

“Rick Niutta, SA Power Networks’ Civil Officer, also worked with a civil contractor who trialled a new installation method for pole footings, driving steel piles into the ground to manage the challenging water issues experienced onsite,” Mr Smith said.

Levels issues and lasers from the Department of Defence’s adjacent site works also proved challenging. 

“They interfered with SA Power Networks’ laser levels so temporary fence screening had to be installed to manage the confusion,” Mr Smith said.

Continued combined efforts will be a launching pad for the defence project, which in addition to keeping Australia safe, will create up to 180 jobs at businesses across the greater Adelaide region.

The expected completion date of the project is July 2022.

Related articles
0 Comments

Leave a reply

Your email address will not be published. Required fields are marked *

*


The reCAPTCHA verification period has expired. Please reload the page.

©2024 Energy Magazine. All rights reserved

CONTACT US

We're not around right now. But you can send us an email and we'll get back to you, asap.

Sending

Log in with your credentials

Forgot your details?