Powerlink replaces 40-year-old transformers from Townsville Substation
Share

Powerlink has completed a $9 million project to replace two 40-year-old transformers at Garbutt Substation, securing the power supply for the Townsville region. 

Powerlink Interim Chief Executive, Kevin Kehl, said that on-ground work to replace the ageing transformers started in early 2018 and was completed over several stages.

“Garbutt Substation is a critical part of the transmission network in this area, supplying power to Townsville CBD, the airport precinct and busy port area.

“These two 98 tonne transformers, standing 4.5m high, were transported to site in mid-2018 and work has progressed since then to safety install them within the existing substation.

“This project supported 15 jobs during construction and ensures a continued safe and reliable supply for Townsville into the future.”

Mr Kehl said the transformers were originally installed in the 1970s and had reached the end of their service life.

“The original Garbutt Substation was built back in the 1950s, and was gradually developed to keep up with demand as Townsville grew into the busy regional centre it is today.

“These transformers were about 40-years-old and had served the region well over that time.

“Their job is to convert high voltage electricity from Powerlink’s transmission network down to a lower voltage suitable for Ergon Energy’s distribution network, which in turn delivers electricity to households and businesses.

“The two new 100MVA transformers will deliver a safe, secure and reliable supply to help meet the region’s needs.”

Related articles
0 Comments

Leave a reply

Your email address will not be published. Required fields are marked *

*


The reCAPTCHA verification period has expired. Please reload the page.

©2024 Energy Magazine. All rights reserved

CONTACT US

We're not around right now. But you can send us an email and we'll get back to you, asap.

Sending

Log in with your credentials

Forgot your details?