ElectraNet and Trangrid’s EnergyConnect project is progressing, with early works such as surveying, undergrounding overhead lines and camp construction awarded to local contractors, and 1,500 new jobs expected to be created.  

ElectraNet and Transgrid’s EnergyConnect project is rapidly progressing, with early work activities such as surveying, undergrounding overhead lines and camp construction already being awarded to a range of local, state and interstate businesses, offering various opportunities for local trades.

The EnergyConnect electricity transmission infrastructure aims to save NSW customers $180 million a year.

Some of the early works in the western section that have been awarded include:

  • Australian Portable Camps, based in South Australia, has been awarded the contract to build the first camp construction near Mildura with flow-on effects for local trades; accommodation camps will be established for the majority of workers, with five other camps located in NSW around Balranald, Hay, Jerilderie and Lockhart
  • Underground contracting has been awarded to overhead contractor, TOBCO, a Sydney based company that has a Southern Regional Office in Yass, NSW
  • Early works surveying has been awarded to Land Survey, a Sydney-based company
  • Early works test drilling has been awarded to SMEC Australia based in Sydney with regional offices in Newcastle and Wollongong
  • Milsearch, an Australian family‐owned company based in Canberra, has been engaged to search for unexploded ordnance on EnergyConnect’s project alignment in the Wentworth area

Executive Manager of Delivery, Craig Stallan, said, “Transgrid is getting on with the delivery of the NSW component of the project – a 700km transmission line from the SA border to the regional energy hub of Wagga Wagga.

“We are building backbone infrastructure which will transform the electricity network for the future, support the South West Renewable Energy Zone and enable the transition to a decarbonised economy,” Mr Stallan said. 

“The project provides opportunities to a wide range of businesses and will create up to 1,500 jobs over the next two and a half years, in areas like Wagga Wagga and in key manufacturing centres – providing a boost to regional economies.”

Jobs will include construction, road transport, accommodation, cleaning services, catering, fencing, surveying and geotechnical services, labourers and trades, plant operators and construction engineers.

“Our construction partner SecureEnergy has begun awarding a number of early works activities to a range of businesses. These packages involve work to be carried out for undergrounding of services contracting, land surveys and the first camp construction,” Mr Stallan said. 

SecureEnergy is expected to begin work in the western section of the corridor in 2022, which includes works between the NSW and SA Border, Transgrid’s Buronga substation and the NSW and Victorian border near Monak.

David Whatmough, SecureEnergy Project Director, said, “SecureEnergy is recruiting for a range of positions and skill levels for the delivery of the project and to support the workforce. 

“We are filling a number of these roles with local candidates as part of our commitment to support local communities.”

SecureEnergy will soon begin advertising for a wide range of other services including flights, coaches, constructing other camps, fuel supply, construction water, vehicle wash-downs and industrial waste, providing opportunities for suppliers, including Indigenous businesses.

Juan Luis Barrenechea, SecureEnergy Deputy Project Director, said, “We are committed to working collaboratively with all communities including local Indigenous people in providing employment, training and business opportunities.

“We feel a great sense of responsibility towards the continued success of all our employees once the project they are working on is finished. 

“We are committed to providing skills and opportunities that can be transitioned from the project to the local region and to build individual skills and capabilities for their future endeavours.”

Works packages are found on the Industry Capability Network (ICN) website here: https://icn.org.au.

Suppliers can find more information by going to the SecureEnergy website and accessing the Supplier Information Guide: www.secureenergyjv.com.au.

Related articles
0 Comments

Leave a reply

©2024 Energy Magazine. All rights reserved

CONTACT US

We're not around right now. But you can send us an email and we'll get back to you, asap.

Sending

Log in with your credentials

Forgot your details?