Energy lightbulbs
Share

AusNet Services is seeking an increase in its allowed revenue to fund the final stage of installation for Rapid Earth Fault Current Limiters (REFCLs), and has submitted an application to the AER.

Funding for a “contingent project” is permitted under clause 6.6A.2 of the National Electricity Rules through an adjustment to the maximum allowed revenue under AusNet Services 2016-20 revenue determination.

Network revenue determinations are made by the AER and set out the revenue network businesses can collect from electricity consumers through charges within a defined period.

Interested parties are invited to make submissions on AusNet Services’ contingent project application by 26 July 2019.

Related articles
0 Comments

Leave a reply

Your email address will not be published. Required fields are marked *

*


The reCAPTCHA verification period has expired. Please reload the page.

©2024 Energy Magazine. All rights reserved

CONTACT US

We're not around right now. But you can send us an email and we'll get back to you, asap.

Sending

Log in with your credentials

Forgot your details?